#1
07-28-2009, 05:17 PM
What kind of hand checks should we perform before the detail analysis and design of a steel structure? What should we check briefly so as to be sure that no major mistake happens by the use of the software?

Regards
F.



[-] The following 2 users Like fashion's post:2 users Like fashion's post
  • Grunf, Grunf
 kaungthant

Not-Activated

White-private
User ID: 477
Joined: Jan 2009
Posts: 67
Threads: 22
Likes: 265 in 29 posts
Given Likes: 434
Points:3,660 EP
#2
07-28-2009, 05:26 PM
(07-28-2009, 05:17 PM)fashion Wrote: What kind of hand checks should we perform before the detail analysis and design of a steel structure? What should we check briefly so as to be sure that no major mistake happens by the use of the software?

Regards
F.

It is better to use the software only for analysis and you should design your structure by hand calculation or you can write a program using Microsoft Excel.



[-] The following 2 users Like kaungthant's post:2 users Like kaungthant's post
  • Grunf, Grunf
 rendel_©

Not-Activated

Philippine
User ID: 1138
Joined: Mar 2009
Posts: 231
Threads: 122
Likes: 2,115 in 214 posts
Given Likes: 2687
Points:18,845 EP
#3
07-29-2009, 01:25 AM
Compute the column reaction by area method roughly and compare it to your analysis result, should be almost the same.



[-] The following 2 users Like rendel_©'s post:2 users Like rendel_©'s post
  • Grunf, Grunf
 hsccindia

Not-Activated

White-private
User ID: 3182
Joined: Jul 2009
Posts: 11
Threads: 6
Likes: 79 in 5 posts
Given Likes: 225
Points:716 EP
#4
07-29-2009, 04:07 AM
The major checks we used to apply are:

1) Tributary area calculation and comparing it with analysis result,
2) checking and matching the base shears, scaling factor should not be less than 1,
3) arbitrary checking moments for the beams,
4) I am using Staad pro, so model should be checked thorughly and moments should be released secomdary beams.

Regards



[-] The following 4 users Like hsccindia's post:4 users Like hsccindia's post
  • Grunf, Grunf, levanduy, levanduy
 fashion

Not-Activated

White-private
User ID: 3328
Joined: Jul 2009
Posts: 75
Threads: 15
Likes: 282 in 41 posts
Given Likes: 188
Points:3,082 EP
#5
07-29-2009, 07:04 PM
(07-29-2009, 04:07 AM)hsccindia Wrote: The major checks we used to apply are:

1) Tributary area calculation and comparing it with analysis result,
2) checking and matching the base shears, scaling factor should not be less than 1,
3) arbitrary checking moments for the beams,
4) I am using Staad pro, so model should be checked thorughly and moments should be released secomdary beams.

Regards

1) u mean tributary area of the loads on the slabs?
2) scaling factor is?




  •
 raxitpatel

Not-Activated

White-private
User ID: 3472
Joined: Jul 2009
Posts: 2
Threads: 0
Likes: 16 in 2 posts
Given Likes: 0
Points:233 EP
#6
07-30-2009, 03:01 AM
Before starting 3D model in Etabs or any software I perform following task as my preliminary design and atleast to give preliminary structure depth and size to Architect in meetings.

1. I have created simple load takedown spreadsheet. Which considers tributary area and uniform load load on each level to calculate reaction at base. That will also help to quickly size interior and exterior column and foundation for talking and comparing purpose.

2. Calculate quickly total wind exposure area * wind load = total base shear

3. For floor framing use basic thumb rules like if beam span is 34 ft, for composite floor system the beam depth would be atleast half of it (34/2 = 17). Therefore most likely W18 sections (For US codes).

4. Sometimes I also quickly model my lateral system (Brace or moment frames) in one single line attached to each other with rigid link in RISA to get the preliminary sizes of braces. My observation indicates that generally the final design is within 10 to 15% difference.

Please share your thoughts and ideas. That will help everyone to improve the engineering steps and quality of work both.



[-] The following 2 users Like raxitpatel's post:2 users Like raxitpatel's post
  • rendel_©, rendel_©
 iceman84

Not-Activated

White-private
User ID: 1829
Joined: May 2009
Posts: 245
Threads: 48
Likes: 419 in 154 posts
Given Likes: 402
Points:8,906 EP
#7
07-30-2009, 10:23 AM (This post was last modified: 07-30-2009, 10:26 AM by iceman84.)
Checks are one thing, predimensioning is another thing.
Predimensioning can be based on different criteria like strength, stifness or ductility.
In my opinion checks should be made after finishing the analysis (checks for equilbrium of the node, check for base shear, check for tributary area, etc.). Another check is that of the modes of vibration (eigenperiods, eigenshapes, mass participation factors) and compare the results from the analysis with the results obtained using a simplified method (like Rayleigh). The eigenperiods should be compared with the values obtained using the simplified formulas.




  •
 fashion

Not-Activated

White-private
User ID: 3328
Joined: Jul 2009
Posts: 75
Threads: 15
Likes: 282 in 41 posts
Given Likes: 188
Points:3,082 EP
#8
08-01-2009, 07:49 AM
Is there any book about the simplified Rayleigh method?




  •
 iceman84

Not-Activated

White-private
User ID: 1829
Joined: May 2009
Posts: 245
Threads: 48
Likes: 419 in 154 posts
Given Likes: 402
Points:8,906 EP
#9
08-01-2009, 04:36 PM
(08-01-2009, 07:49 AM)fashion Wrote: Is there any book about the simplified Rayleigh method?

I think this method is explained in books of Dynamics of Structures. In Romania this method is shown in an annex of the Seismic Design Code.




  •
 shark

Not-Activated

White-private
User ID: 4238
Joined: Aug 2009
Posts: 4
Threads: 1
Likes: 2 in 2 posts
Given Likes: 77
Points:354 EP
#10
08-22-2009, 11:27 AM
i want to know, how we calculate length of shear wall required for a building? what formulas involved? im using British Standard. Thank you




  •
« Next Oldest | Next Newest »

Users browsing this thread: 1 Guest(s)
Pages (2): 1 2 Next »



  • View a Printable Version
  • Subscribe to this thread

Designed by CivilEA - Powered by MyBB

Linear Mode
Threaded Mode