According to me this is quite normal here in Mauritius since after construction has started, there are many variations that are made by the promoter and because of these changes, we'll have to redesign and reissue construction plans. But once we've (the structural engineer) have approved the steel drawings which the contractor send to us, we stick to it, no further changes are allowed unless its critical.
Regards
Parwez