09-24-2010, 09:03 AM
Dear members of Civilea
I need help.
I did CSM procedure manually of course with help of ETABS & excel
What 'target displacement' that I should enter at the pushover case for CSM procedure ?
Should I calculate first "the target displacement" as in FEMA 273/356 & enter that 'target displ. of FEMA 273/356' to the pushover case ?
Thanks
Paladin
I need help.
I did CSM procedure manually of course with help of ETABS & excel
What 'target displacement' that I should enter at the pushover case for CSM procedure ?
Should I calculate first "the target displacement" as in FEMA 273/356 & enter that 'target displ. of FEMA 273/356' to the pushover case ?
Thanks
Paladin