@knrsa
Please indicate your problem with specifics. Like, what is the column size, load and footing size and loadings
The reason for the footing retrofit.
Level of detailing and calculations depend on these specifics.
If you have only one footing to repair, you would do it conservatively because the cost engineering time will exceed the repair cost
Or if you have too many of these footings , it might offset the engineering cost.
The location of these footings are also important, located at inside or outside of the building can effect the detail
Basically the detail / arrangement you are showing is correct.
Regards
Please indicate your problem with specifics. Like, what is the column size, load and footing size and loadings
The reason for the footing retrofit.
Level of detailing and calculations depend on these specifics.
If you have only one footing to repair, you would do it conservatively because the cost engineering time will exceed the repair cost
Or if you have too many of these footings , it might offset the engineering cost.
The location of these footings are also important, located at inside or outside of the building can effect the detail
Basically the detail / arrangement you are showing is correct.